Eugene,

We have ordered several R710 servers in the last few months - accessories/etc were received within 2-3 business days, the servers themselves within 3 weeks (within the time frame promised in the order).   

Historically, we've never had any real worries about Dell delivering within their time frames (having placed many orders every year for the last 7 years).  I think there was only one case where we had to escalate, and this got tracked down to the shipping companies fault (Dell sent out a new system for us immediately).

The current delay of 3 weeks is a little higher than the 2 weeks I would normally expect or even the 1 week I've seen on occasion - but not enough to keep us from placing future orders.

It's possible that only certain classes of accounts or models are being impacted.  Ultimately, you have to be able to trust your dell account rep -- if you feel he's not giving you the right information, you should ask to be switched to a different one.  Sometimes you have to push to be given a real answer; I've definitely had to do that on a few occasions - but you should never have to put up with being strung along.

Matt

----- "Paras pradhan" <pradhanparas at gmail.com> wrote:

> I got mine 4 weeks before. We placed the order around 8 weeks before.
> 
> 
> Paras.
> 
> 
> 
> On Tue, Jan 5, 2010 at 4:39 PM, < cue at elkconsulting.com > wrote:
> 
> 
> I apologize for this being a bit off topic.
> 
> Is anyone else waiting on a PowerEdge server delivery for over 45 days
> now?
> I keep getting delayed notices for my orders and my Dell account rep
> (we're
> small-med company) seems to be at a loss.
> 
> Because they keep telling me the server is going to be there in a week
> or
> so, it prevents me from ordering another server (which will take 2+
> weeks).
> I'm starting to think that I'm being strung along (so I don't cancel
> my
> order) until whatever the problem is get's fixed. I don't believe that
> a
> company like Dell can miscalculate part delivery times (or even not
> know
> them) by as much as 45 days.
> 
> Update:
> It seems they are deleting posts on the dell community where people
> are
> trying to figure out why their poweredge servers being delayed (and
> google
> doesn't cache it):
> 
> http://www.google.com/search?sourceid=navclient&ie=UTF-8&rlz=1T4GGLL_enUS336
> US336&q=PowerEdge+server+shipping+delays
> 
> Eugene
> 
> _______________________________________________
> Linux-PowerEdge mailing list
> Linux-PowerEdge at dell.com
> https://lists.us.dell.com/mailman/listinfo/linux-poweredge
> Please read the FAQ at http://lists.us.dell.com/faq
> 
> 
> _______________________________________________
> Linux-PowerEdge mailing list
> Linux-PowerEdge at dell.com
> https://lists.us.dell.com/mailman/listinfo/linux-poweredge
> Please read the FAQ at http://lists.us.dell.com/faq

-- 
Matthew Marlowe - http://www.deploylinux.net/
CEO @ DeployLinux Consulting, Inc
matt at deploylinux.net, 858-400-7430
http://www.twitter.com/deploylinux